
CAPTEC Engineering, Inc.
301 NW Flagler Ave.
Stuart, Florida 34994
Tel: (772) 692-4344
Fax: (772) 692-4341
captecinfo@gocaptec.com
Merritt Island & Central Florida Gas Pipelines
• These projects were completed for NUI- City Gas of Florida
• CAPTEC completed the design, permitting and utility Construction Engineering and Inspection (CEI) services for 11 miles of an 8 inch high pressure steel pipeline throughout Merritt Island and the Kennedy Space Center at Cape Canaveral Air Station. This project included 3600 feet of directional drilling.
• CAPTEC also completed the design, permitting and construction engineering inspection services for 90 miles of 12 inch and 8 inch steel pipe and approximately 24 miles of 2 - 4 inch size service pipes along the SR 80 corridor from West Palm Beach to Ft Meyers. This is known as NUI's Central Florida Gas Pipeline.