Merritt Island & Central Florida Gas Pipelines

• These projects were completed for NUI- City Gas of Florida

• CAPTEC completed the design, permitting and utility Construction Engineering and Inspection (CEI) services for 11 miles of an 8 inch high pressure steel pipeline throughout Merritt Island and the Kennedy Space Center at Cape Canaveral Air Station. This project included 3600 feet of directional drilling.

• CAPTEC also completed the design, permitting and construction engineering inspection services for 90 miles of 12 inch and 8 inch steel pipe and approximately 24 miles of 2 - 4 inch size service pipes along the SR 80 corridor from West Palm Beach to Ft Meyers.  This is known as NUI's Central Florida Gas Pipeline.